Data centres: impact of the draft National Policy Statement

26 November 2026

The Department for Business, Innovation, Science and Trade has got the industry talking after releasing a draft National Policy Statement (NPS) for data centres. This document has been expected for a long time, and is shaped by the government’s recognition of data centres as essential infrastructure. 

With the consultation closing in January 2027, there are a few elements that may impact data centre development in England which anyone involved (or considering involvement) in these projects needs to be aware of, explain Jade Garner and Harry Cross, Associate EIA Leads at DM . 

Get your site selection right

The main change the NPS outlines is the importance of site selection. This doesn’t just mean finding a site that balances environmental, design and land consent constraints, but thoroughly documenting the selection process. As such, origination work will be frontloaded even more than before. 

In addition for the importance of getting your routing and siting methodology right, the Environmental Statement (ES) has to be robust, with a well-evidenced mitigation hierarchy against potential significant effects. 

Bringing in constraints mapping and spatial analysis at the first stage assists significantly with this process. A high-level planning analysis of any consents and designations, plus reviews from an environmental and land ownership perspective, will also help develop a full evidence base to justify your decision. 

As well as helping from a planning and timeline perspective, this demonstrates that your site finding mission was thorough, correct and rigorous. 

If you do, consent will be presumed

By developing a comprehensive document which sets out your site decision-making process, then the NPS states consent will be presumed by the Secretary of State if all relevant criteria are met. In fact, if all regulations are considered, environmental impacts are mitigated and design requirements are implemented, then refusal would be exceptional. 

A person in an orange high-visibility jacket stands by a metal gate overlooking cows grazing in a green field under cloudy skies.

Environmental requirements haven’t changed…

The draft NPS does not propose any major changes to environmental legislation. The Infrastructure Planning (Environmental Impact Assessment) Regulations 2017, Habitat Regulations Assessments (HRA) under the Conservation of Habitats and Species Regulations 2017 and Biodiversity Net Gain (BNG) regulations under the Environment Act 2021 all still apply, alongside environmental permitting. 

BNG and HRA requirements are also newly applicable to Nationally Significant Infrastructure Projects (NSIPs). 

Any permit applications need to be submitted alongside a Development Consent Order (DCO). Plus, the Environment Agency must also be engaged at least six months before a planning application. 

The presumption of consent if environmental requirements are met is the biggest change. It means the volume of pre-application work will increase to prove these stipulations have been considered. This must include the mitigation hierarchy, emissions assessment and alternative energy generation sources. 

For clustered projects, a cumulative impact assessment must assess in combination effects.

…but design requirements have

When it comes to land requirements, the NPS emphasises the importance of responsible resource usage. Applicants must disclose annual and peak water use, power usage effectiveness and justify their server cooling designs. Heat re-use is fundamental to this, meaning local networks which can use excess heat need to be linked to. 

The need for this additional infrastructure is likely to lead to an expansion of sites and land use. To ensure power resilience, cable routing to existing infrastructure (particularly renewables) or grid connections need to be considered. This is where a thorough optioneering process needs to be followed and documented. Then, if the most resource-efficient design isn’t chosen, this needs to be justified. 

An aerial view of a large industrial facility with a white roof, green facade panels, and rows of rooftop equipment beside paved roads.

NSIP thresholds are confirmed

It’s confirmed in the NPS that data centre projects with a minimum threshold of 100MW of rated IT load capacity can choose to go through the NSIP and DCO process. This puts the Secretary of State as the decision maker and can be considered under section 35 direction of the Planning Act 2008. 

Smaller projects can also opt into the scheme, or decide to go through the local planning route. This is an important consideration for developers, as different consenting routes have various requirements, processes, timescales and associated costs. 

Land competition is likely to increase

Strategic land values may be pushed up in locations where NPS guidance can be followed to derisk consent completely. Requirements such as  water availability and heat distribution networks also means the number of sites considered by developers will be narrowed down. 

As a result, there’ll be a significant drive to secure the sites in the best possible positions as quickly as possible. Having regional offices full of different experts means we can quickly react to these demands and get on the ground to meet client needs.

Thank you

Jade and Harry would like to thank fellow colleagues at DM, Jen Richards MCIfA, Associate Archaeologist, and Dan Pugh, Associate Land Referencer, for their contribution to this article.

Specialist contacts

A smiling man with dark hair and a beard wears a white button-down shirt against a red background.
Environment & Planning

Harry Cross

Associate - EIA
A smiling woman with long wavy hair wearing a polka-dot top, shown against a solid red background.
Environment & Planning

Jade Garner

Associate - EIA

Related articles